Part A)

First thing that Shuzwolrd wants to do is that they want to increase their level of production from 1300 to 2800 units. At the moment, there is no forecast that demand is going to increase, but they want to stay one step ahead and lay a platform for future growth. If the move turns out to be profitable one, the transportation schedule that is implemented at the moment is likely to change. This is one of the recommendations that the transportation cost per month must be minimized and delivery plan is laid to ensure that it happens.

One more challenge that is faced at the moment is that plant was their first major project in China, but beside that they have some other plants as well that are located in Hangzhou and Fuzhou. They are the female shoes that are prepared by them is carried out in these facilities. The products are hurled to company's three main storehouses due to the purpose of allocation towards their regional warehouses as well as their offline retail stores and major shopping center. In the graphs, below the monthly production of the Shuzworld that is produced at each of their plants and the subsequent monthly requirements so that the demand that is present at the stores can be taken care of.

In order to increase the amount of production carried out at the local level, company's executive has been paying attention on the expenditures transformation with the warehouses of company's outlet F 3 and some other transport expenses. The costs are estimated to be around $ 6 per unit. The following table below table could be used to investigate the whole thing. The sum outlays of the distribution is said to be around $ 13,630,

Factory

Capacity

Warehouse

Requirements

Shanghai

1300

1

2500

Shuzworld H

2300

2

1500

Shuzworld F

2200

3

1800

Totals

5800

6

5800

Using this data that is provided by the managers of Shuzworld, it can be used to build a transportation system that is matrix less. The data above can be summarized to get the clear picture of what is needed to be done as it corresponds to the availability of the supplies and constraints of the demand to bring down the total cost of the delivery.

From /To

Warehouse 1

Warehouse 2

Warehouse 3

Factory Capacity

Shanghai

$4

$3

$3

2500

Shuzworld H

$3

$4

$2

1500

Shuzworld F

$2

$4

$6

1800

Warehouse Requirement

1300

2300

2200

5800

Even though basic task is to ensure that the lowest possible cost of the transport by looking at the shipping plan. To accommodate and take care of the plants in the Shanghai has increased from 1300 to 2800. The analysis of the tool transportation must be used to make sure that the lower costs can be found out. The make sure that the better and cheaper shipping methods can be found out. At the same time, there is a need to add a fourth destination to gauge the effectiveness of the supply and demand while bringing the cost of the mission down to a certain level. The following diagrams are defining the new shipping cost as the production has increased. It is to be seen that ...